Effect of Delay due to U-Turn on Pangeran Antasari Road (Case Study U-Turn Near Ganesha Operation)

Authors

  • Yovi Dwiana
  • Sasana Putra
  • Rahayu Sulistyorini

DOI:

https://doi.org/10.23960/jrsdd.v8i4.1624

Abstract Views: 95 File Views: 133 File Views: 0

Abstract

Pangeran Antasari road is an urban road with 2-ways 4-lanes type (using median). In this median was found U-turn facility near of Ganesha Operation. Based on preliminary observations at the study location (Pangeran Antasari Road), it was seen there vehicles that could’t make a smooth U-Turn movement and other vehicles that were obstructed when passing through this facility, especially during peak hours when traffic volume was high.

The objevtives of this study is to know the effect of U-Turn on delays in Pangeran Antasari road, which is near of Ganesha Operation. The method used is Gap Acceptance. It was to determine the value of vehicle travel time that is affected by U-Turn movement vehicles, namely the gap time and follow-up time.

Based on the data analysis carried out at the U-Turn near of Ganesha Operation, it can be concluded that the effect of delay is due to the average time of gap accepted and follow-up time. The average time value of gap accepted was 3.64 seconds and 4.35 seconds in the morning and 9.59 seconds and 8.78 seconds in the afternoon. The average follow-up time of the vehicle is 12.72 seconds to 18.2 seconds in the morning and 14.01 seconds to 17.87 seconds in the afternoon.

Downloads

Download data is not yet available.

References

Dharmawan, Indra dan Oktarina (2013). Kajian Putar Balik (U-Turn) Terhadap Kemacetan Ruas Jalan di Perkotaan (Studi Kasus Jalan Teuku Umar dan Jalan Z.A Pagar Alam Kota Bandar Lampung). Jurnal. Surakarta : Konferensi Nasional Teknik Sipil 7

Departemen Pekerjaan Umum Dirjen Bina Marga, (2014). Pedoman Kapasitas Jalan Indonesia. Jakarta : Departemen Pekerjaan Umum

Kasan, M., Listiawati, H., Mashuri. (2005). Pengaruh U-Turn Terhadap Karakteristik Arus Lalu-Lintas di Ruas Jalan Kota Palu (Studi Kasus Jl. Moh. Yamin. Universitas Tadulako. Palu

Liliani, Titi (2002). Perencanaan Dan Teknik Lalulintas. Penerbit ITB, Bandung.

Obaidat, Turki (2013). Gap Acceptance Behavior at U-Turn Median Openings –

Case Study in Jordan. Jordan Journal of Civil Engineering, vol. 7

Downloads

Published

2021-11-13

How to Cite

Dwiana, Y., Putra, S., & Sulistyorini, R. (2021). Effect of Delay due to U-Turn on Pangeran Antasari Road (Case Study U-Turn Near Ganesha Operation). Jurnal Rekayasa Sipil Dan Desain, 8(4), Hal. 831 – 840. https://doi.org/10.23960/jrsdd.v8i4.1624

Issue

Section

Makalah Ilmiah Edisi Desember 2020