Analisis Percepatan Durasi Proyek Dengan Menggunakan Metode Crashing

Authors

  • I Dewa Made Agung Pramana
  • Amril Ma'ruf Siregar
  • Dwi Herianto

DOI:

https://doi.org/10.23960/jrsdd.v8i2.1354

Abstract Views: 126 File Views: 316 File Views: 0

Abstract

There are possible problems arise during construction of project that can cause delays. Delays can cause losses in the form of fines, overhead costs, additional salaries and rental tools and other. To overcome the problems, there are some ways to achieve project completion in due time.

The purpose of this study was to analyze the acceleration of the project duration by utilizing crashing method and its impact on project cost. The object of the case study was the construction of Lampung Regional Police Headquarter. The scenario utilized was increased the number of workers by 35% and the added working hours by four hours. 

The results show by increasing the number of workers across eleven project activities, the project duration was crashed to 252 days or two days earlier than the scheduled time and the project cost was decrease to Rp. 23,964,647,646.00 or 0.908% lower than the scheduled cost. The results also show by adding four more working hours across ten project activities, the project duration was crashed to 253 days or one day earlier than the scheduled time and the project cost was decreased to Rp. 23,995,417,215.00 or 0.781% lower than the scheduled budget.

 

Keywords: Project Acceleration, Crashing method, increase of the number of workers, the addition of working hours

Downloads

Download data is not yet available.

References

Hansen , Seng. 2015. Manajemen Kontrak Konstruksi. Jakarta: Gramedia Pustaka Utama.

Husen, Arbar. 2009. Managemen Proyek. Yogyakarta: Andi Offset.

Project Management Institute. 2017. Kerangka Ilmu Manajemen proyek PMBOK Guide. Jakarta: PMI Indonesia Chapter.

Rachman, Taufiqur. 2012. Manajemen Proyek (Crashing Project). Jakarta: Universitas Esa Unggul.

Widiasanti, Irika dan Lenggogeni. 2013. Manajemen Konstruksi. Bandung: Remaja Rosdakarya offset.

Santoso, Wahyu. 2017. Analisa Percepatan Proyek Menggunakan Metode Crashing dengan Penambahan jam kerja empat Jam dan Sistem Shift Kerja. Skripsi. Yogyakarta: Universitas Islam Indonesia.

Downloads

Published

2021-11-13

How to Cite

Pramana, I. D. M. A., Siregar, A. M., & Herianto, D. (2021). Analisis Percepatan Durasi Proyek Dengan Menggunakan Metode Crashing. Jurnal Rekayasa Sipil Dan Desain, 8(2), Hal. 347 – 356. https://doi.org/10.23960/jrsdd.v8i2.1354

Issue

Section

Makalah Ilmiah Edisi Juni 2020