Analisis Perbandingan Biaya Pembangunan Jembatan Menggunakan Konstruksi Konvensional dan Pre-cast ( Study Kasus TOL SUMATERA, Paket 4, Jalur 8 Ruas Bandar Jaya )

Authors

  • Aditya zulkarnain
  • Martono Hadi
  • I Wayan Diana

DOI:

https://doi.org/10.23960/jrsdd.v6i4.940

Abstract Views: 95 File Views: 0 File Views: 0

Abstract

Bridges are one of the most important means of transportation for humans. In the construction of bridge construction, there are 2 methods used namely conventional and pre-cast methods. Both of these methods have differences in the construction of the upper building structure alone.

 

In the pre-cast bridge construction: When the work for the upper structure of the building is 59 days, the number of workers is 130 people, the work barriers are not too constraining the traffic. Whereas in conventional bridge construction: The work time is 110 days, the number of workers is 104, the obstacle of work will hamper the traffic below. From the analysis of the two types of bridges, pre-cast bridges are 20% more expensive than conventional bridges, but the pre-cast bridge work time is 51 days faster.

Keywords : Pre-cast bridge construction, Conventional bridge construction .

Downloads

Download data is not yet available.

References

Peraturan Menteri PU, 2013, Peraturan Mentri Pekerjaan Umum Nomor 11/PRT/M/2013 tentang Pedoman Analisa Harga Satuan Pekerjaan, Bidang Pekerjaan Umum. Jakarta

Surat Edaran Menteri PU, 2013, Surat Edaran Menteri Pekerjaan Umum Nomor 02/SE/M/2013 tentang Pedoman Analisa Harga Satuan Pekerjaan, Bidang Pekerjaan Umum. Jakarta

Hutama Karya TRANS SUMATRA, 2015, Kriteria Desain DIVISI JALAN TOL Ruas Bakauheni – Terbanggi Besar.

Bina Marga, 2010, Spesifikasi Umum Bina Marga “Struktur” Divisi 7, Department PU, Jakarta.

Bina Marga, 2013, Standar Konstruksi Jembatan Tipe Balok T B.M.100, Department PU, Jakarta.

SNI 07-2052.2002, Baja Tulangan Beton, Badan Standarisasi Nasional (BSN)

Sukirman, S., 2003, Perkerasan Jalan Raya, Penerbit NOVA, Bandung.

Published

2018-11-07

How to Cite

zulkarnain, A., Hadi, M., & Diana, I. W. (2018). Analisis Perbandingan Biaya Pembangunan Jembatan Menggunakan Konstruksi Konvensional dan Pre-cast ( Study Kasus TOL SUMATERA, Paket 4, Jalur 8 Ruas Bandar Jaya ). Jurnal Rekayasa Sipil Dan Desain, 6(4), Hal. 335 – 344. https://doi.org/10.23960/jrsdd.v6i4.940

Issue

Section

Makalah Ilmiah Edisi Desember 2018